September 11, 2018

Receipt of Order from Tokyo for "Kanamachi Water Purification Plant - Integrated Monitoring and Control Equipment Construction Project (No. 2)"

Overview of construction

1. Construction name

Receipt of Order from Tokyo for "Kanamachi Water Purification Plant - Integrated Monitoring and Control Equipment Construction Project (No.2)"

2. Contractee

Bureau of Waterworks Tokyo Metropolitan Government

3. Contract date

August 6, 2018

4. Location

1-1 Kanamachi Water Purification Plant, Katsushika-ku, Tokyo

5. Contract amount

1,177,200,000 yen (including tax)

6. Contractor

METAWATER Co., Ltd.

7. Overview of construction

Integrated monitoring operating system (new construction; tabletop unit-type) 1set
Water transmission and distribution facility interface system (new construction; indoor independently closed-type) 1set
Substation facility interface system (new construction; indoor independently closed-type) 1set
Facility management terminal (new construction; tabletop unit-type) 1set
Integrated monitoring and control equipment modification (modification; indoor independently closed-type, tabletop unit-type) 1set
Water intake facility interface system modification (modification; indoor independently closed-type) 1set
Sophisticated water treatment facility interface system modification (modification; indoor independently closed-type) 1set
Filtration tank facility interface system modification (modification; indoor independently closed-type) 1set
Chemical dosing facility interface system modification (modification; indoor independently closed-type) 1set
Instrumentation input and output system modification (modification; indoor independently closed-type) 1set
Voice alarm system modification (modification; indoor independently closed-type) 1set
Water operating center transmission system modification (modification; indoor independently closed-type) 1set
Equipment management system modification (modification; indoor independently closed-type, tabletop unit-type) 1set
Filtration tank monitoring and control equipment modification (modification; indoor independently closed-type, tabletop unit-type) 1set
Sophisticated water treatment monitoring and control equipment modification (modification; indoor independently closed-type, tabletop unit-type) 1set
Supplementary work 1set

Project period

August 7, 2018 to January 27, 2021