Receipt of Order from Kawasaki City, Nagasawa Water Treatment Plant—Secondary Thickening System Installation Project for Wastewater Treatment

Overview of construction

1. Construction name

Nagasawa Water Treatment Plant—Secondary Thickening System Installation Project for Wastewater Treatment

2. Contractee

Waterworks Bureau, City of Kawasaki

3. Contract date

March 15, 2019

4. Tendering method

Comprehensive evaluation, open tendering method (specifically simplified type)

5. Location

5-1-1 Mita, Tama-ku, Kawasaki City


6. Contract amount

1,108,080,000 yen (including tax)


7. Contractor

METAWATER Co., Ltd.


8. Overview of construction


	Secondary thickening system installation   one set
 

9. Project period

March 15, 2019 to November 3, 2020