METAWATER

News

News Release
09.11.2018

Receipt of Order from Osaka Prefecture for “South Osaka Gulf Basin Sewerage System — Chubu Mizu Mirai Center — Second Water Treatment Electric Equipment Renewal Project”

Overview of construction

1. Construction name

Receipt of Order from Osaka Prefecture for “South Osaka Gulf Basin Sewerage System — Chubu Mizu Mirai Center — Second Water Treatment Electric Equipment Renewal Project”

2. Contractee

Osaka prefecture

3. Contract date

August 1, 2018

4. Tendering method

Open tendering (comprehensive evaluation bidding method with post-qualification assessment type)

5. Location

Nishiki Minami-machi, Kaizuka-shi, Osaka (within premises)


6. Contract amount

1,674,000,000 yen (including tax)


7. Contractor

MATAWATER Co., Ltd.


8. Overview of construction

・Monitoring and control system  1 set
・Operation system  1 set
・Instrumentation system  1 set
・Manufacturing / Installation / Adjustment  1 set
 

9. Project period

August 1, 2018 to February 28, 2022